At an automotive lighting supplier, service lead time on an imported controller was stopping production. The modular EHRTC-RM2 and 3-business-day service moved downtime into planned shift breaks.

Situation

The plant moulds headlamp housings and reflectors on an 8-zone hot runner mould that ran on an imported controller. When one zone’s power stage failed, the whole unit went abroad for service; with no spare, the mould waited 2–3 weeks. Two faults a year meant roughly two weeks of lost production.

Solution

The mould was commissioned on an EHRTC-RM2, 8 zones:

  • Each zone’s power stage sits on its own module, so the faulty module is removed and shipped while the other 7 zones keep running.
  • Auto-Tune was run per zone at commissioning; manifold zones were split to respect the 3200 W limit.
  • The deviation alarm was set to ±8 °C and the alarm relay wired to the moulding machine’s “temperature ready” input.
  • Stand-By at 120 °C for weekend stops; Monday heat-ups use Soft-Start.

Result

No unplanned stops in six months of follow-up. In month three an SSR on one module was replaced; the module came back within 3 business days and the swap took 10 minutes between shifts. Zone temperatures stayed within ±1 °C and flash-related scrap disappeared from the quality log.

Note: This page represents a scenario typically observed with EHRTC-RM2 users; company name and measured values will be updated with customer approval.

Demo unit programme

Try it on your own mould before you buy

We ship an EHRTC demo unit matching your zone count to your plant, with remote support for installation and parameter setup. Trial terms and duration are agreed together.

  • PM1 or RM2 demo unit sized to your zone count
  • Remote support for installation, Auto-Tune and alarm setup
  • Decide with your own production data at the end of the trial
EHRTC-RM2 demoDemo unit

Let’s pick the right controller for your project

Send us your zone count, mould type and heater loads; we’ll reply with the best configuration and a price quote the same business day.

WhatsApp